Learn first
A release needs evidence about the right version
A version identifies a particular set of changes. A test gives evidence about the version tested. Deployment makes a version available in a stated environment.
How to work it out Check that the tested version matches the proposed release. Keep permission, data correctness, recovery time, and availability as separate checks.
A separate example A passing test for a separate package 8 does not establish that changed package 9 passes. Retest the changed version before relying on the old result.
The recovery point objective (RPO) limits the time gap between the recovered data point and the outage. The recovery time objective (RTO) limits the whole interruption until service is working again. Compare each measured interval with its own maximum. Meeting one limit does not meet both. A rehearsal is evidence, not a promise about every future outage.
Worked example
An outage is at 09:20. A copy covers data through 09:12, so the data gap is 8 minutes. Detection takes 1 minute, restoration 3 and checking 2, so service returns after 6 minutes. Limits of 10 minutes for the data gap and 6 for interruption are both met, including the exact time limit.
Three separate paper rehearsals
The outage is at 14:30. The maximum data gap is 15 minutes and the maximum interruption is 8 minutes. A covers data through 14:05: detection 2, restore 1, checks 3 minutes. B covers through 14:26: detection 1, restore 2, checks 7 minutes. C covers through 14:15: detection 2, restore 3, checks 3 minutes. Each copy passes its own content checks. Stages are sequential, include all delays, and service returns only after checks finish. Each row is a separate rehearsal, not time added to another row. No real records are changed.